Powell Middle School – Addition and Renovations
Project Team
PBA Project Manager:
Kathy Buchanan
Architect: Cope
Associates
Contractor: Johnson &
Galyon Construction
Scope
Existing Building:
Renovating 89,533 SF
Addition: New
Construction 62,365 SF Includes new gymnasium.
Total: 151, 898 SF
Budget
Total Project Budget:
16 million.
Schedule
Construction commenced on
June 9, 2007.
Phase 1 (Addition) Scheduled
for Completion: August, 2008
Phase 2, 3 and 3A
(Renovation of Existing Building) Scheduled for Completion:
August, 2009
Status
Masonry walls are under
construction for the new addition.

Classrooms on North Side of Gymnasium Wall
|