Skatepark

 

 Skatepark

 

 Project Team

 Project Manager:  Kathy Buchanan

 Design Build Contractor:  California Skateparks, Wally Hollyday Designer.

 

 Scope

 Skatepark being constructed in Tyson Park

 

 Budget

 Total Project Budget:  $542,000.00

 

 Schedule

 Construction commenced on August 16, 2007.

 Scheduled for Completion:  December 21, 2007

 

 Status

 Shotcrete is being installed at the bowls.

 

 