UT Build-Out at
Burlington Library
Project
Team
PBA
Project Manager: Dan Martin
Architect:
Studio Four Design
Contractor:
Johnson & Galyon, Inc.
Scope
The
Burlington Library, located at 4614 Asheville Hwy. has
approximately 6,000 S.F. of retail space
adjoined to the west. This space is planned to be built-out
by the County for the University of Tennessee to have
outreach programs for the College of Nursing, Architecture,
Business and Education/Health/Human Sciences within this
area.
Budget
Total
Project Budget: $250,000
Schedule
Facility
is scheduled to be complete by the end of January 2008.
Status
Work
has begun on the project and will be complete in 8-10
weeks. The University will be leasing 3,865 S.F. from
Knox County.
|